Generator load test
INS-2208 · Fallowmere House · Jan 14, 2027 · Doug Pettibone
Checklist · 5 items
- PassFuelFuel level at or above three-quarters
- PassBatteryBattery and charger normal
- FailTransferTransfer time 10 seconds or lessTransfer took 14 seconds on two attempts.Corrective action CA-305
- PassRun30-minute run under building load
- PassLogTest log signed
Summary
- Status
- Completed
- Score
- 80% (4 of 5 passed)
- Started
- Jan 14, 10:00 AM
- Completed
- Jan 14, 11:10 AM
- Inspector
- Doug Pettibone
Corrective actions (1)
- Generator transfer time 14 secondsOpenCA-305 · Doug Pettibone · due Jan 28, 2027WO-4054Generator transfer switch slow — 14 secondsOn hold