Make-ready — Apt 134
WO-4028 · The Linden at Harrow Creek · Unit 134
In progressScheduledTurnoverAged · open 31 days
Description
Standard make-ready after move-out: patch and paint, flooring, deep clean, safety device tests, fixture check.
History
- Work startedJan 9, 8:10 AM · Andre Lyle
- AssignedJan 8, 9:20 AM · Tomas Reyna
- Created from turnoverJan 8, 9:05 AM · Gwen Halvorsen
Details
- Assigned to
- Andre Lyle
- Requested by
- Gwen Halvorsen
- Created
- Jan 8, 9:05 AM
- Due
- Jan 17, 2027 · 22 days late
- Open for
- 31 days
- Source
- Turnover TO-1131
- Apartment